Building Fee Schedule
State surcharge is $.00265 per cubic foot on new buildings & additions.
For all others, the State surcharge is $1.35 per $1000.
Minimum fee for each subcode is $50.00.
New Building $.030 per cubic foot
Addition $.030 per cubic foot
Alteration: first $50,000 $30 per $1000
Alteration: next $50,000 $24 per $1000
Alteration: over $100,000 $18 per $1000
Roofing R3/R5 $50.00
Siding R3/R5 $50.00
Fence $50.00
Sign $2.00 per square foot
Pool - Above Ground $150.00
Pool - In Ground $500.00
Asbestos Abatement $150.00
Lead Hazard $150.00
Demolition $2,500.00
Demolition, R3 less than 5000 sf, 30ft $250.00
Certificate of Occupancy (CO) $50.00
CO Asbestos $50.00
Certificate of Continued Occupancy (CCO) $200.00
Use Group Change $200.00
Certificate for Clearance for Lead $100.00
 
Electrical Fee Schedule
Minimum Fee is $50.00
Receptacles and Fixtures
First 50 $40.00
Each additional -25 $ 10.00
 
Motors & Electrical Devices over 1 hp
Up to 10 hp $15.00
Up to 50 hp $50.00
Up to 100 hp $100.00
Larger than above $500.00
 
Transformers & Generators over 1 kw
Up to 10.0 kw $15.00
Up to 45.0 kw $50.00
Up to 112.50 kw $100.00
Larger than above $500.00
 
Service Panels, Entrances and Subpanels
Up to 200 amps $50.00
Up to 1000 amps $100.00
Larger than above $500.00
Pool $150.00
 
Plumbing Fee Schedule
Minimum Fee is $50.00
Water Closet $15.00
Urinal / Bidet $15.00
Bath Tub $15.00
Lavatory $15.00
Shower $15.00
Floor Drain $15.00
Sink $15.00
Dishwasher $15.00
Drinking Fountain $15.00
Washing Machine $15.00
Hose Bibb $15.00
Stacks $15.00
Water Heater $45.00
Fuel Oil Piping $40.00
Gas Piping $25.00
Steam Boiler $75.00
Hot Water Boiler $75.00
Sewer Pump $75.00
Interceptor / Separator $75.00
Backflow Preventer $15.00
Grease Trap $75.00
Sewer Connection $75.00
Water Service Connection $75.00
 
Fire Protection Fee Schedule
Minimum Fee is $50.00
Storage Tanks
Storage Tanks $50.00
 
Alarm / Supervisory / Signaling
First 12 $50.00
Each additional 50 $50.00
 
Wet & Dry Sprinkler Heads
1 - 20 $75.00
21 - 100 $135.00
101 - 200 $240.00
201 - 400 $620.00
401 - 1000 $945.00
Over 1000 $1,150.00
Standard Pipes $240.00
 
Pre-Engineered Systems
Wet Chemical $150.00
Dry Chemical $150.00
CO2 Suppression $150.00
Foam Suppression $150.00
Halon Suppression $150.00
 
Miscellaneous
Kitchen Hood Exhaust System $150.00
Smoke Control Systems $500.00
Gas or Oil Fires Appl $50.00
 
Municipal Ordinance
Certificate of Continuing Occupancy (CCO) $100.00
Emergency CCO (within 72 hours) $150.00
Emergency CCO (within 24 hours) $200.00
(Fees revised as per Municipal Ordinance #18-07 adopted on 5/16/07)